Living the Dream Year 3 Day 85 – Clifty Hill 2 – Day 6 Foundation Block laying

Year 3 Day 85 – “Living the Dream”. Wednesday, 7/26/2023. Clifty Hill 2 – Day 6 Foundation Block laying. 25 bags of Type S Mason mix have been used so far. Picked up another 11 bags in the afternoon. I am acting as the background cheerleader. Those bags weigh 80 pounds. Nope, I can’t liftContinue reading “Living the Dream Year 3 Day 85 – Clifty Hill 2 – Day 6 Foundation Block laying”

Living the Dream Year 3 Day 84 – Clifty Hill 2 – Day 5 Foundation Block laying, compacting soil with running water

Year 3 Day 84 – “Living the Dream”. Tuesday, 7/25/2023. Clifty Hill 2 – Day 5 foundation block laying. By the time Steve gets set up and ready it is really hot. He is soaked and he hasn’t really started yet. Before he starts mixing the cement, he sets the blocks up in a rowContinue reading “Living the Dream Year 3 Day 84 – Clifty Hill 2 – Day 5 Foundation Block laying, compacting soil with running water”

Living the Dream Year 3 Day 83 – Clifty Hill 2 – Day 4 Foundation Block laying

Year 3 Day 83 – “Living the Dream”. Monday, 7/24/2023. Clifty Hill 2 – Day 4 foundation block laying. Another day of not a cloud in the sky. We are filling the Hummingbird feeder every night now. I am not sure if it is the hummingbirds or the hornets that are depleting it so fast.Continue reading “Living the Dream Year 3 Day 83 – Clifty Hill 2 – Day 4 Foundation Block laying”

Living the Dream Year 3 Day 82 – Clifty Hill 2 – Day 3 Block laying

Year 3 Day 82 – “Living the Dream”. Sunday, 7/23/2023. Clifty Hill 2 – Foundation block laying Day three. Not a cloud in the sky and Steve is building the longest block wall he has ever built. This house is 52 feet long. The cement is drying out super-fast in this hot sun. He hasContinue reading “Living the Dream Year 3 Day 82 – Clifty Hill 2 – Day 3 Block laying”

Living the Dream Year 3 Day 81 – Clifty Hill 2 – Day 2 Block laying, three corners completed

Year 3 Day 81 – “Living the Dream”. Saturday, 7/22/2023. Clifty Hill 2 – Next year we are going to do a deck container garden or a greenhouse. Here are some old container garden videos. The hot sun rises all day as the block laying continues in the blazing heat. It is amazing that theContinue reading “Living the Dream Year 3 Day 81 – Clifty Hill 2 – Day 2 Block laying, three corners completed”

Living the Dream Year 3 Day 80 – Clifty Hill 2 – Day 12 Septic system work, Septic system covered

Year 3 Day 80 – “Living the Dream”. Friday, 7/21/2023. Clifty Hill 2 – We planted more green bean seeds in the Jiffy greenhouse. The ones we picked from the existing plants are so yummy. I think we still have enough time for another crop and there is more to pick outside. Can’t wait toContinue reading “Living the Dream Year 3 Day 80 – Clifty Hill 2 – Day 12 Septic system work, Septic system covered”

Living the Dream Year 3 Day 79 – Clifty Hill 2 – Day 11 Septic system work, Inspector final passed, Day 1 block laying

Year 3 Day 79 – “Living the Dream”. Thursday, 7/20/2023. Clifty Hill 2 – First thing this morning the last piece of the pipe was cut and placed in the Septic system. The inspector was called for an inspection and by noon time we had our inspection. The inspector issued the Notice of Release forContinue reading “Living the Dream Year 3 Day 79 – Clifty Hill 2 – Day 11 Septic system work, Inspector final passed, Day 1 block laying”

Living the Dream Year 3 Day 78 – Clifty Hill 2 – Day 10 Septic system work, Last piece of pipe purchased

Year 3 Day 78 – “Living the Dream”. Wednesday, 7/19/2023. Clifty Hill 2 – Septic system is completed except for being short one little piece of pipe from the second D box to the second lateral. We went to Lowes and picked up the last piece of pipe this afternoon. Tomorrow morning the last pieceContinue reading “Living the Dream Year 3 Day 78 – Clifty Hill 2 – Day 10 Septic system work, Last piece of pipe purchased”

Living the Dream Year 3 Day 77 – Clifty Hill 2 – Day 9 Septic system work, tighten excavator tracks

Year 3 Day 77 – “Living the Dream”. Tuesday, 7/18/2023. Clifty Hill 2 – Finally, this morning at 5am we get some rain. A lot of thunder and lightning, but very little rain. There was enough rain to keep down the dust though. We have green beans that are ready to be eaten. Tomorrow IContinue reading “Living the Dream Year 3 Day 77 – Clifty Hill 2 – Day 9 Septic system work, tighten excavator tracks”

Living the Dream Year 3 Day 76 – Clifty Hill 2 – Day 8 Septic system work

Year 3 Day 76 – “Living the Dream”. Monday, 7/17/2023. Clifty Hill 2 – Septic work continues. Did you know that Diesel is heavier than gasoline. It weighs about seven pounds per gallon. Gasoline weighs about six pounds per gallon. Water weights 8.4 pounds per gallon. The difference is due to higher density and theContinue reading “Living the Dream Year 3 Day 76 – Clifty Hill 2 – Day 8 Septic system work”

Living the Dream Year 3 Day 75 – Clifty Hill 2 – Day 7 Septic system work, second lateral in

Year 3 Day 75 – “Living the Dream”. Sunday, 7/16/2023. Clifty Hill 2 – Look Somerset is on the list of 9 Most Charming Towns in Kentucky. https://www.worldatlas.com/…/9-most-charming-towns-in…. More stone was moved today, and the second lateral pipe was placed in. The birds kept their watch. Today’s product recommendations are for keeping your skin lookingContinue reading “Living the Dream Year 3 Day 75 – Clifty Hill 2 – Day 7 Septic system work, second lateral in”

Living the Dream Year 3 Day 74 – Clifty Hill 2 – Day 6 Septic system work, visiting neighbor

Year 3 Day 74 – “Living the Dream”. Saturday, 7/15/2023. Clifty Hill 2 – Moving more stone in the morning before the rain comes. The dirt is so dry that we are covered in dirt dust. It is like a big dust bowl. Every night I wash any shoes I wore next door. At leastContinue reading “Living the Dream Year 3 Day 74 – Clifty Hill 2 – Day 6 Septic system work, visiting neighbor”

Living the Dream Year 3 Day 73 – Clifty Hill 2 – Day 5 Septic system work, Mexican night

Year 3 Day 73 – “Living the Dream”. Friday, 7/14/2023. Clifty Hill 2 – It was a hard long hot sunny 96 degree ten hour day. Almost all of the one hundred tons of 1 1/2 – 2-inch clean stone is in the septic. In the hot afternoon sun in the trenches of the KentuckyContinue reading “Living the Dream Year 3 Day 73 – Clifty Hill 2 – Day 5 Septic system work, Mexican night”

Living the Dream Year 3 Day 72 – Clifty Hill 2 – Day 4 Septic system work, Block delivered

Year 3 Day 72 – “Living the Dream”. Thursday, 7/13/2023. Clifty Hill 2 – Getting ready for block laying. Look at the corn field this year. It looks like a chemical burn to us. Wonder what was put on it? We bought 10 bags of Type S cement. That will do about 250 blocks. HopeContinue reading “Living the Dream Year 3 Day 72 – Clifty Hill 2 – Day 4 Septic system work, Block delivered”

Living the Dream Year 3 Day 71 – Clifty Hill 2 – Day 3 Septic system work,

Year 3 Day 71 – “Living the Dream”. Wednesday, 7/12/2023. Clifty Hill 2 – First septic lateral is almost done. It took 2 truck loads of clean stone. We need another truck load. The neighbor came visiting. Around here they come visiting in Kabota’s. Today’s product recommendations are for keeping your skin looking its bestContinue reading “Living the Dream Year 3 Day 71 – Clifty Hill 2 – Day 3 Septic system work,”

Living the Dream Year 3 Day 70 – Clifty Hill 2 – Day 2 Septic system work

Year 3 Day 70 – “Living the Dream”. Tuesday, 7/11/2023. Clifty Hill 2 – Just another hot Kentucky workday excavating and laying pipe and stone into the first septic system lateral. The concrete footings are dry. Nails are set into the corners of the house to ensure the house is squared before block laying starts.Continue reading “Living the Dream Year 3 Day 70 – Clifty Hill 2 – Day 2 Septic system work”

Living the Dream Year 3 Day 69 – Clifty Hill 2 – Footings poured

Year 3 Day 69 – “Living the Dream”. Monday, 7/10/2023. Clifty Hill 2 – The footings are poured. We ordered 15 yards and used 14. Please ignore me talking about 15,000 yards in the attached videos. Yikes, the stupid things that come out of my mouth. You pay for concrete before it is delivered. TheContinue reading “Living the Dream Year 3 Day 69 – Clifty Hill 2 – Footings poured”

Living the Dream Year 3 Day 68 – Hummingbird party

Year 3 Day 68 – “Living the Dream”. Sunday, 7/09/2023. It is party day at the Hummingbird feeder. Six of them are enjoying a meal and some acrobatic dancing. These Hummingbirds love overcast drizzly days. Today’s product recommendations are for keeping your skin looking its best at sea and in the sun. My favorite skinContinue reading “Living the Dream Year 3 Day 68 – Hummingbird party”

Living the Dream Year 3 Day 67 – Clifty Hill 2 – Ready for concrete

Year 3 Day 67 – “Living the Dream”. Saturday, 7/08/2023. Clifty Hill 2 – Today two chutes were built for the step downs in the footing. The back of the house is a walkout basement, and the left side is a garage. The front and right side will be partially built into the ground. ThatContinue reading “Living the Dream Year 3 Day 67 – Clifty Hill 2 – Ready for concrete”

Living the Dream Year 3 Day 66 – Clifty Hill 2 – Footing complete, rebar set

Year 3 Day 66 – “Living the Dream”. Friday, 7/07/2023. Clifty Hill 2 – The footings excavation is complete, and the rebar is in. The concrete will fill the trenches up to the top of the rebar. This will make it level. The cleanup of the trenches will be done Saturday and Sunday. It isContinue reading “Living the Dream Year 3 Day 66 – Clifty Hill 2 – Footing complete, rebar set”

Living the Dream Year 3 Day 65 – Clifty Hill 2 – Footing excavation started

Year 3 Day 65 – “Living the Dream”. Thursday, 7/06/2023. Clifty Hill 2 – Steve started digging the footings. It was a haircut day for me. Those pesky moles. Every time Steve fixes the driveway, they come and dig new tunnels. Steve feeds the birds and then attacks them with his truck. New Jersey? Today’sContinue reading “Living the Dream Year 3 Day 65 – Clifty Hill 2 – Footing excavation started”

Living the Dream Year 3 Day 64 – Clifty Hill 2 – SKRECC marked where new roadside pole will be set

Year 3 Day 64 – “Living the Dream”. Wednesday, 7/05/2023. Clifty Hill 2 – An SKRECC representative showed up today. He marked the spot where they will be installing a new roadside pole with a transformer. All poles that have electrical wires going to houses must have a transformer. More than one house can runContinue reading “Living the Dream Year 3 Day 64 – Clifty Hill 2 – SKRECC marked where new roadside pole will be set”

Living the Dream Year 3 Day 63 – Happy Fourth, food and family

Year 3 Day 63 – “Living the Dream”. Tuesday, 7/04/2023. Wishing everyone a very Happy 4th of July. Hope you had a great time celebrating the anniversary of when the Second Continental Congress adopted the Declaration of Independence on July 4, 1776. The USA officially became an independent nation on this day in 1776, henceContinue reading “Living the Dream Year 3 Day 63 – Happy Fourth, food and family”

Living the Dream Year 3 Day 62 – Clifty Hill 2 – Septic tank in place

Year 3 Day 62 – “Living the Dream”. Monday, 7/03/2023. Clifty Hill 2 – More excavation work completed, and the septic tank was set in place and covered. Never stop dreaming – ALL THINGS ARE POSSIBLE!! Put some action to that dream and get moving. Today’s product recommendations are for keeping your skin looking itsContinue reading “Living the Dream Year 3 Day 62 – Clifty Hill 2 – Septic tank in place”

Living the Dream Year 3 Day 61 – Off day, tornado warning oops

Year 3 Day 61 – “Living the Dream”. Sunday, 7/02/2023. The firework show must have been fantastic on Lake Cumberland last night. From the Williamsburg you could see them bursting with color behind the trees. I think at Clifty Hill 2 you will be able to see them clearly. The show lasted for about 45Continue reading “Living the Dream Year 3 Day 61 – Off day, tornado warning oops”

Living the Dream Year 3 Day 60 – Clifty Hill 2 – Moving topsoil, homesite video

Year 3 Day 60 – “Living the Dream”. Saturday, 7/01/2023. Clifty Hill 2 – We want to be sure to preserve the topsoil for future landscaping. The topsoil is being moved out of where Clifty Hill 2 house will be built and placed in piles for later. We will have separate piles of fill andContinue reading “Living the Dream Year 3 Day 60 – Clifty Hill 2 – Moving topsoil, homesite video”

Living the Dream Year 3 Day 59 – New Excavator tracks, Williamsburg strong marketing

Year 3 Day 59 – “Living the Dream”. Friday, 6/30/2023. Steve is so excited about new rubber excavator tracks. He wanted me to take pictures. They weigh over 300 pounds each. The 18-wheeler could not get to our house yesterday. Steve met him out on the highway, and they transferred them to his truck. ThoseContinue reading “Living the Dream Year 3 Day 59 – New Excavator tracks, Williamsburg strong marketing”

Living the Dream Year 3 Day 58 – Clifty Hill 2 – Corners squared, stone for driveway and septic delivered

Year 3 Day 58 – “Living the Dream”. Thursday, 6/29/2023. Clifty Hill 2 – The house corners are squared, marked, and staked. 24.5 tons of Dense Graded Aggregate Base stone for the driveway and two loads of 1 1/2 – 2-inch clean stone for the septic bed were delivered. Stone prices are a lot higherContinue reading “Living the Dream Year 3 Day 58 – Clifty Hill 2 – Corners squared, stone for driveway and septic delivered”

Living the Dream Year 3 Day 57 – Williamsburg for sale

Year 3 Day 57 – “Living the Dream”. Wednesday, 6/28/2023. Big day. Put the Williamsburg up for sale. 1511 Clifty Hill Rd, Science Hill, KY 42553 | realtor.com® 1511 Clifty Hill Rd, Science Hill, KY 42553 | MLS #23012247 | Zillow https://www.tiktok.com/t/ZT8RePX7F/ https://www.facebook.com/reel/1389111678303534 https://www.facebook.com/reel/285705507363287 Today’s product recommendations are for keeping your skin looking its bestContinue reading “Living the Dream Year 3 Day 57 – Williamsburg for sale”

Living the Dream Year 3 Day 56 – Clifty Hill 2 – Driveway work

Year 3 Day 56 – “Living the Dream”. Tuesday, 6/27/2023. Clifty Hill 2 – Today was another decorating day. I am the shopping queen right now. I like spending money, but enough is enough. It is amazing how far we have come in two years. Steve worked on the driveway for the home next door.Continue reading “Living the Dream Year 3 Day 56 – Clifty Hill 2 – Driveway work”