Year 5, Day 343 “Living the Dream”. Wednesday, 4/08/2026, Clifty Hill 3. Steve was up and out before sunrise to jackhammer the rock.



By noon time the water line, tracer, and hydrant had been installed by Dick’s Plumbing.





















Inspector will be here on Friday. We were able to backfill the ditch in the afternoon . PVC pipes were placed at intervals where the inspector can look at the line and tracer. He can also measure the depth of the trench at those points. It took 160 gallons of water to fill the water line to the hydrant.

The internet company came out and inspected all lines and boxes to the house. They said everything is working perfectly. We decided it must be a router issue. While changing the router we discovered the connection into our old router had burn marks. A new internet router was installed and within a few hours the internet cut out again. Well, apparently that wasn’t the issue. Internet company can not find the issue with our internet.


Other interesting news. We put up a mail box for Clifty Hill 3.



Thoughts to ponder.




Here’s a link to today’s Amazon recommendation: https://amzn.to/4tuk8Mi Concrete Knee Boards 30×8 Inch Just bought these for new home cement floor work. Making things easier.
As an Amazon Associate, I earn from qualifying purchases. #CommissionsEarned
Follow The Journey
Get new daily posts delivered directly to your inbox.